This seawall site sits at the end of a residential canal in Englewood. During a major storm, runoff moving across the land toward the canal scoured out the soil behind the seawall. The washout undermined the wall, left a collapsed bank behind it, and carried sand and debris into the canal.

Sarasota County hired WB Williamson Bros. to repair the damage. The scope covered dredging the washed out material, replacing 80 feet of seawall, and building a concrete deck and stairs at the water’s edge.

LOCATION

Englewood, Sarasota County, FL

PROJECT TYPE

Dredging, seawall replacement, and concrete deck

WALL LENGTH

80 feet

PRIMARY CHALLENGE

Damage that started on the land side, not the water side

The Client’s Situation

Most seawall problems start at the water. This one started on land. A large volume of storm runoff reached the shoreline, washed out the soil the wall depended on, and left the County with two problems: a damaged wall with an open cut behind it, and roughly 24 cubic yards of sediment sitting in the canal.

The open washout was also a safety concern for the surrounding homes.

What Made This Project Challenging

Two Kinds of Damage at Once

The wall itself had been undermined, but the larger problem was the missing ground behind it. Replacing the wall without restoring the bank, or restoring the bank without addressing the canal, would have left the job half done.

The soil that once supported the wall was now on the canal bottom. It had to be dredged out before the new wall could go in.

The site sits between homes at the end of the canal. Crews worked in a narrow area while containing turbidity in the water and protecting nearby storm drains.

Clearing the Canal and Replacing the Wall

We set turbidity barriers in the canal and inlet protection around nearby storm drains, then dredged approximately 24 cubic yards of washed out sediment and debris.

The new wall is a Truline seawall system. Its vinyl forms were set along the canal end, reinforced with #8 hot dipped galvanized rebar, and filled with a specialized concrete mix. The 80 foot wall follows the shape of the canal end and ties back into the shoreline on each side. With the wall in place, the bank behind it was rebuilt.

Storm washout and collapsed bank behind the old seawall in Englewood before replacement
Concrete stairs and deck under construction at the new Englewood seawall

A Concrete Deck and Stairs Where the Washout Was

On top of the new wall, we built a 125 square foot concrete deck with stairs leading down toward the water and an aluminum safety handrail. Where the collapsed slope used to be, there is now a solid, finished edge.

The Finished Result

The canal end has gone from an open washout and a shoaled canal to a continuous new seawall, a rebuilt bank, and usable access at the water. The sediment is out of the canal, and the area behind the wall is level ground again.

For another seawall rebuilt after a failure, see our North Fort Myers seawall replacement.

Finished Truline seawall with concrete stairs and aluminum handrail in Englewood
Finished concrete deck along the new seawall at the Overbrook site in Englewood

Materials and Specifications

  • Approximately 24 cubic yards of dredged storm washout material
  • 80 linear feet of Truline seawall
  • #8 hot dipped galvanized (HDG) rebar
  • Specialized concrete fill mix
  • 125 sq. ft. concrete deck
  • Concrete stairs with aluminum safety handrail
  • Turbidity barriers and storm drain inlet protection during construction

When Storm Runoff Threatens a Seawall: What to Watch For

Seawalls are built to hold back soil, but water moving toward them from land can do damage too. Property owners and public works crews in Englewood and across Sarasota County should watch for:

  • Low spots where runoff collects and flows toward the wall
  • Soft ground or small sinkholes directly behind the cap
  • Gaps opening between the cap and the soil
  • Fans of sediment in the canal after heavy rain
  • Clogged or damaged drain inlets near the shoreline

Catching drainage problems early costs far less than dredging a canal and replacing a wall.

Seawall Construction Backed by Four Generations

Let's Talk About Your Project

Since 1996, WB Williamson Bros. has built and replaced seawalls for homeowners, communities, and public agencies across Southwest Florida. From storm damage repair and dredging to new seawall construction, our team can evaluate the site and recommend the right approach.

Call 239-283-2013 or fill out the form below to schedule a consultation.

Building Partnerships That Last
Name
Service Type
error: Content is protected !!